Deluca Project update #4

With this great weather we are having this week the guys are hard at with the final few pours on the fire wall. Yesterday was a quick hour & half pour into 8ft of the Plasti Fab ICF wall.

We will have 16ft left on the fire wall to set up and pour then the concrete work for walls will be complete. Once the walls have all been completed our next step is to start installing all the roof trusses.